高大支模架专项方案(专家论证)

目 录

第一章 工程概况 ................................................................................................................................................................ 2

一、工程概况简要说明 ................................................................................................................................................ 2 二、超重梁构件情况说明(地下室部分) ................................................................................................................ 2 三、超高梁、板构件情况(共享大厅、雨棚部分) ................................................................................................ 3 第二章 编制原则和依据 .................................................................................................................................................... 3

一、编制范围及原则 .................................................................................................................................................... 3 二、编制依据 ................................................................................................................................................................ 3 第三章 设计理念及材料要求 ............................................................................................................................................ 4

一、支撑体系的设计理念 ............................................................................................................................................ 4 二、材料要求 ................................................................................................................................................................ 4 第四章 支架搭设方案 ........................................................................................................................................................ 4

一、搭设流程 ................................................................................................................................................................ 4 二、构造要求 ................................................................................................................................................................ 4

1、立杆 .................................................................................................................................................................. 4 2、水平杆 .............................................................................................................................................................. 5 3、剪刀撑 .............................................................................................................................................................. 5 4、其它 .................................................................................................................................................................. 5 5、搭设参数、详图 .............................................................................................................................................. 5

第五章 模板制作与安装说明 ............................................................................................................................................ 5

一、准备工作 ................................................................................................................................................................ 5

1、模板拼装 .......................................................................................................................................................... 5 2、模板的基准定位工作 ...................................................................................................................................... 5 二、模板支设工艺 ........................................................................................................................................................ 6

1、梁、板模板 ...................................................................................................................................................... 6

第六章 模板的拆除、堆放方案 ........................................................................................................................................ 6

一、模板拆除 ................................................................................................................................................................ 6 第七章 施工管理与安全措施 ............................................................................................................................................ 6

一、安全组织机构框架图 ............................................................................................................................................ 6 二、技术交底 ................................................................................................................................................................ 7 三、搭设验收 ................................................................................................................................................................ 7 四、过程管理 ................................................................................................................................................................ 8

1、施工前管理 ...................................................................................................................................................... 8 2、施工中管理要点 .............................................................................................................................................. 8 3、质量管理措施 .................................................................................................................................................. 9 五、砼浇捣管理 ............................................................................................................................................................ 9

1、准备工作 .......................................................................................................................................................... 9 2、浇注顺序 ........................................................................................................................................................ 10 3、浇注方法 ........................................................................................................................................................ 10 4、浇注施工注意事项 ........................................................................................................................................ 10 六、重大危险源辨识 .................................................................................................................................................. 10

1、机械伤害 ........................................................................................................................................................ 10 2、触电 ................................................................................................................................................................ 10 4、物体打击 ........................................................................................................................................................ 11 5、高处坠落 ........................................................................................................................................................ 11 6、坍塌 ................................................................................................................................................................ 11 7、起重伤害 ........................................................................................................................................................ 11 8、高温 ................................................................................................................................................................ 11 七、安全管理措施 ...................................................................................................................................................... 11 八、监测措施 .............................................................................................................................................................. 11

1、监测控制 ........................................................................................................................................................ 12 2、监测点设置 .................................................................................................................................................... 12 3、监测措施 ........................................................................................................................................................ 12 4、仪器设备配置 ................................................................................................................................................ 12 5、监测说明 ........................................................................................................................................................ 12 6、监测频率 ........................................................................................................................................................ 12 九、应急预案 .............................................................................................................................................................. 12

1、高处坠落和物体打击事故应急救援预案 .................................................................................................... 12 2、触电事故应急救援预案 ................................................................................................................................ 12 3、机械伤害应急救援预案 ................................................................................................................................ 13 4、模板、脚手架坍塌 ........................................................................................................................................ 13 5、消防事故应急救援预案 ................................................................................................................................ 13 6、高温中暑的应急 ............................................................................................................................................ 14 7、项目部安全急救援预案 ................................................................................................................................ 14

第八章 支模架计算书 .................................................................................................................................................. 14

Page 1 of 70

1、400×1550梁模板支架计算书 .............................................................................................................................. 14 2、400×1550梁侧模板支架计算书 .......................................................................................................................... 22 3、800×700梁模板支架计算书 ................................................................................................................................ 27 4、800×700梁侧模板支架计算书 ............................................................................................................................ 33 5、400×1100梁模板支架计算书 ............................................................................................................................... 37 6、400×1100梁侧模板支架计算书 ........................................................................................................................... 43 7、350×800梁模板支架计算书 ................................................................................................................................ 48 8、350×800侧模板支架计算书 ................................................................................................................................ 53 9、80厚板模板支架计算书 ....................................................................................................................................... 58 10、120厚板模板支架计算书 ................................................................................................................................... 63

第一章 工程概况

一、工程概况简要说明

工程名称:XXX扩建工程新建病房楼;地址:周巷镇周西公路51-139号;本工程由慈溪市公共项目建筑中心(局)投资建设,山东省建筑设计研究院设计,浙江有色建设工程有限公司地质勘察,英泰克工程顾问(上海)有限公司监理,方远建设集团股份有限公司组织施工;由郑金跃担任项目经理,周海军担任技术负责人。

本工程结构类型为框架结构;长130.2m,宽46.2m。该楼地下一层,地上八层,总建筑面积28644.50㎡,其中地下一层为地下车库,建筑面积4174.3㎡,地上八层为住院部大楼,建筑面积24470.2㎡。

结构层楼面标高、结构标高

机房屋面 屋面 8 7 6 5 4 3 设备层 2 首层 -1 层号 38.600 34.360 30.560 26.760 22.960 19.160 15.360 11.560 8.660 4.160 -0.040 -4.240 标高(m) 4.240 3.800 3.800 3.800 3.800 3.800 3.800 2.900 4.500 4.200 4.200 层高(m) C30 C30 C35 C35 C35 C35 C35 C35 C45 C45 C45 C45 砼标号 本工程地下室共有两种规格梁的线荷载超出20KN/m,属超重支模架;共享大厅和雨棚梁、板支模架垂直高度超出8m,属超高支模架。

地下室支架立杆搭设于地下室底板上,底板厚度400,底板板面标高-4.240,顶板厚度160。地下室3~19/A~C轴梁面标高-0.9,支模架高度为3.340米。地下室1~19/C~L轴梁面标高-0.04支模架高度为4.200米。

共享大厅和雨棚支架立杆搭设在地下室顶板上,地下室顶板厚度160,顶板板面标高有-0.04和-0.9。共享大厅位于13~16/C~E轴,梁面标高8.660米,楼板板厚120,从地下室顶板面-0.040算起,高度8.700米。雨棚位于13~16/A~C轴,梁面标高8.660米,楼板板厚80,从地下室顶板面-.0900算起,高度9.560米。 二、超重梁构件情况说明(地下室部分)

AKL19:400×1550 位于10~19/C轴 计算高度3.340米 Page 2 of 70

AKL27:400×1550 AKL10:800×700 位于3~9/C轴 位于6/C~D轴 计算高度3.340米 计算高度4.200米 三、超高梁、板构件情况(共享大厅、雨棚部分)

YPKL:400×1100 YPLL2:200×800 YPLL1:200×400 YPKL1a:200×400 楼板:80厚 BKL5:350×800 BKL8:350×650 BKL9:350×800 BL13:250×650 BKL20:300×700 BL14:250×600 BKL22:250×650 BL16:250×700 楼板:120厚

位于13~16/A~C轴 位于13~16/A~C轴 计算高度9.560米 计算高度9.560米 位于13~16/A~C轴 计算高度9.560米 位于13~16/A~C轴 位于13~16/A~C轴 位于13/C~E轴 位于14/C~E轴 位于16/C~E轴 计算高度9.560米 计算高度9.560米 计算高度8.700米 计算高度8.700米 计算高度8.700米 位于13~16/C轴南侧 计算高度8.700米 位于13~16/C轴 计算高度8.700米 位于13~16/C轴北侧 计算高度8.700米 位于13~16/D轴 位于13~16/E轴 位于13~16/C~E轴 计算高度8.700米 计算高度8.700米 计算高度8.700米 第二章 编制原则和依据

一、编制范围及原则

1、本方案编制范围为超高、超重模板支架,普通模板支架搭设已另外编制。

2、本施工方案编制将遵循四项基本原则,即一是符合性原则;二是先进性原则,三是合理性原则,四是符合工程质量、工期要求及安全生产、文明施工要求的原则。 二、编制依据

1、建质【2009】87号文件

2、《建筑结构荷载规范》(GB50009-2001) 3、《混凝土结构设计规范》(GB50010-2002) 4、《建筑施工计算手册》江正荣著 5、《建筑施工手册》第四版

6、《建筑施工脚手架实用手册》杜荣军著 7、《钢结构设计规范》(GB50017-2003)

8、《建筑施工扣件式钢管脚手架安全技术规范》(JGJ 130-2001); 9、《建筑施工扣件式钢管模板支架技术规程》DB33/1035-2006; 10、《扣件式建筑脚手架用钢管》DB33/588-2005; 11、《建筑施工模板安全技术规范》JGJ162-2008; 12、《建筑施工高处作业安全技术规范》(JGJ80-91) 13、《混凝土结构工程施工质量验收规范》(GB50204-2001) 14、《建筑工程施工质量验收统一标准》(GB50300-2001) 15、建设工程安全生产管理条例 16、建筑施工安全检查标准(JGJ59-99)

17、本工程的设计图纸、岩土工程勘察报告、施工组织设计 18、品茗支模架安全计算软件(浙江省标2009-版本V6.0.3.120) 19、其他有关的规范、规程、及参考资料文献资料

Page 3 of 70

第三章 设计理念及材料要求

一、支撑体系的设计理念

在保障安全可靠的前提下,梁与板整体支撑体系设计的一般原则是:立杆步距要一致,便于统一搭设;立杆纵或横距一致,便于立杆有一侧纵横向水平杆件拉通设置;构造要求规范设置,保证整体稳定性和满足计算前提条件。

根据我公司当前模板工程工艺水平,结合设计要求和现场条件,决定采用扣件式钢管架作为本模板工程的支撑体系。 1、梁支撑选用材料:

模板采用18㎜厚胶合板,龙骨为60×80㎜松木;梁侧模用M12对拉螺栓,采用钢管加固;支撑系统采用48×3.5钢管(计算时按48×3.0进行),立杆下垫板为200×200×50木板,超高支模架立杆底部采用16#槽钢铺设。

2、板支撑选用材料:

模板采用18㎜厚胶合板,横楞为60×80㎜松木,支撑系统采用48×3.5钢管(计算时按48×3.0进行),立杆下垫板为200×200×50木板,超高支模架立杆底部采用16#槽钢铺设。 二、材料要求

搭设模板支架用的钢管、扣件,使用前必须进行抽样检测,抽检的数量按有关规定执行。未经检测和检测不合格的一律不得使用。

1、钢材技术性能必须符合《碳素结构钢》(GB700-88)的要求。

2、支架钢管应采用现行国家标准《直缝电焊钢管》(GB/T13793)或《低压流体输送用焊接钢管》(GB/T3092)中规定的 3号普通钢管,其质量应符合现行国家标准《碳素结构钢》(GB/T700)中Q235-A级钢的规定。

3、每根钢管的最大质量不应大于25kg。 4、钢管的尺寸和表面质量应符合下列规定: (1)应有产品质量合格证;

(2)应有质量检验报告,钢管材质检验方法应符合现行国家标准《金属拉伸试验方法》(GB/T228)的有关规定,质量应符合该规范第3.1.1条的规定;

(3)钢管表面应平直光滑,不应有裂缝、结疤、分层、错位、硬弯、毛刺、压痕和深的划道; (4)钢管外径、壁厚、断面等的偏差,应分别符合规范规范(JGJ130-2001)的规定; (5)钢管必须涂有防锈漆。

(6)钢管弯曲变形应符合规范(JGJ130-2001)规定。 (7)钢管上严禁打孔。

5、扣件式钢管脚手架应采用锻铸制作的扣件,其材质应符合现行国家标准《钢管脚手架扣件》(GB15831)的规定。 6、扣件的验收应符合下列规定:扣件应有法定检测单位的测试报告和产品质量合格证。 (1)扣件使用前应进行质量检查,有裂缝、变形的严禁使用,出现滑丝的螺栓必须更换。 (2)扣件均应进行防锈处理。

(3)支架采用的扣件,在螺栓拧紧扭力达65N.m时,不得发生破外。

7、方木选用本地区质量好的材料,不得使用有腐朽、霉变、虫蛀、折裂、枯节的木材,同时应符合木结构设计规范和木结构工程施工质量验收规范的规定。胶合板技术性能必须符合《混凝土模板用胶合板》(ZBB70006-88)要求。

第四章 支架搭设方案

一、搭设流程

支撑排架搭设流程:立杆定位放线→铺设垫板(槽钢)→放置立杆→放置扫地杆→第一步纵向水平杆→第一步横向水平杆→如此重复往上→设置剪刀撑→放置方木、模板→检查验收。 二、构造要求

1、立杆

(1) 地下室梁支模架立杆支承在400厚混凝土底板上,立杆下垫200×200×50木板。共享大厅支模架立杆支承在地下室160厚顶板上,为保证支撑系统的稳定性,搭设共享大厅及雨棚支模架时,地下室下部对应的支模架不拆;由于上下层梁轴线

Page 4 of 70

联系客服:779662525#qq.com(#替换为@)