PMP¿¼ÊÔ¹Ù·½ÑùÌâ

D. Establish a benchmark

64. Íê³É¶¨Ò巶Χ¹ý³Ìºó£¬ÏîÄ¿¾­ÀíӦʹÓÃÄÄÏî¼¼ÊõÀ´Éú³É¿É¿¿¹ÀËã²¢¹ÜÀí³É±¾ºÍ»î¶¯³ÖÐø

ʱ¼ä£¿ A. ·Ö½â

B. ½ôǰ¹Ø¼ü»æÍ¼·¨ C. ÕõÖµ¹ÜÀí D. È·Á¢»ù×¼

65.At a project status meeting, the vendor reports that they will miss the deadline to release software, which will be required for the project to move forward. What should the project manager do first? A. Update the project management plan

B. Negotiate a new release date with the vendor C. Perform the change control process D. Issue a change request for approval

65. ÔÚ״̬»áÉÏ£¬¹©Ó¦É̱¨¸æËûÃǽ«»áÑÓÎóÈí¼þ·¢²¼ÆÚÏÞ£¬¶ø·¢²¼Èí¼þÊÇÏîÄ¿¼ÌÐøÍÆ½øµÄÒ»

¸ö±ØÒªÌõ¼þ¡£

ÏîÄ¿¾­ÀíÊ×ÏÈÓ¦¸Ã×öʲô£¿ A. ¸üÐÂÏîÄ¿¹ÜÀí¼Æ»®

B. Ó빩ӦÉÌЭÉÌÒ»¸öÐµķ¢²¼ÈÕÆÚ C. Ö´Ðбä¸ü¿ØÖƹý³Ì D. Ç©·¢±ä¸üÇëÇó»ñµÃÅú×¼

66.A web development firm delivers a product to the client on time and 20% over the original budget. The client is currently soliciting bids for a new web project. What should the web development firm¡¯s project manager do during the closure phase to enhance customer relations?

A. Request requirements for the new web project B. Conduct a stakeholder analysis

C. Meet with the client to review lessons learned

D. Implement corrective actions of the budget controlling

66. Ò»¼ÒÍøÂ翪·¢¹«Ë¾°´Ê±Ïò¿Í»§½»¸¶²úÆ·£¬µ«³¬³öԭʼԤËã20%¡£¿Í»§Ä¿Ç°ÕýÔÚΪһ¸öÐÂ

ÍøÂçÏîĿͶ±ê¡£ÈôÒªÔöÇ¿¿Í»§¹ØÏµ£¬ÍøÂ翪·¢¹«Ë¾µÄÏîÄ¿¾­ÀíÔÚÊÕβ½×¶ÎÓ¦Ôõô×ö£¿ A. Ë÷È¡ÐÂÍøÂçÏîÄ¿µÄÐèÇó B. ½øÐиÉϵÈË·ÖÎö

C. Óë¿Í»§¿ª»á£¬Éó²é¾­Ñé½Ìѵ D. Ö´ÐÐÔ¤Ëã¿ØÖÆµÄ¾ÀÕý´ëÊ©

67.Theproject manager begins to close a supplier contract. In order to ensure the correct acceptance of the contract, which of the following completing sequence should the project manager follow?

A. Verify completed work, close financial work, close contract B. Close contract, verify completed work, close financial work C. Close financial work, close contact, verify completed work

D. Verify completed work, close contract, close financial work

67. ÏîÄ¿¾­Àí¿ªÊ¼ÊÕβһ¸ö¹©Ó¦É̺Ïͬ¡£ÎªÈ·±£ÕâЩºÏͬÕýÈ·ÑéÊÕ£¬Ó¦°´ÕÕÏÂÁÐÄÄÒ»¸ö˳Ðò

Íê³É£¿

A. ºËʵÒÑÍê³ÉµÄ¹¤×÷¡¢²ÆÎñÊÕβ¡¢ºÏͬÊÕβ B. ºÏͬÊÕβ¡¢ºËʵÒÑÍê³ÉµÄ¹¤×÷¡¢²ÆÎñÊÕβ C. ²ÆÎñÊÕβ¡¢ºÏͬÊÕβ¡¢ºËʵÒÑÍê³ÉµÄ¹¤×÷ D. ºËʵÒÑÍê³ÉµÄ¹¤×÷¡¢ºÏͬÊÕβ¡¢²ÆÎñÊÕβ

68.Due to a budget reduction, a project is terminated in the implementation phase. The project manager is asked to formally close the project What should the project manager do next?

A. Update the change management plan as part of project closure

B. Draft lessons learned with the team and add to the historical database C. Request an increase in the budget so that the project can continue D. Continue to manage project communications

68. ÓÉÓÚÔ¤Ëã¼õÉÙ£¬ÏîÄ¿ÔÚÖ´Ðн׶ÎÖÕÖ¹ÁË¡£ÏîÄ¿¾­Àí±»ÒªÇóÕýʽÊÕβÏîÄ¿¡£

ÏîÄ¿¾­ÀíÏÂÒ»²½Ó¦¸ÃÔõô×ö£¿

A. ¸üбä¸ü¹ÜÀí¼Æ»®£¬×÷ΪÏîÄ¿ÊÕβµÄ×é³É²¿·Ö B. ÓëÍŶӯð²Ý¾­Ñé½Ìѵ£¬²¢Ìí¼Óµ½ÀúÊ·Êý¾Ý¿â C. ÇëÇóÔö¼ÓÔ¤Ë㣬ÈÃÏîÄ¿¼ÌÐø D. ¼ÌÐø¹ÜÀíÏîÄ¿¹µÍ¨

69.A division of a corporation undertakes a one-year integration project. At the end of the second month, the project status report shows the project is progressing according to plan. The corporate office announces this division will be sold in three months

What should the project manager do next?

A. Communicate with the project sponsor and the key stakeholders to validate if

the project is still relevant B. Suspend the project immediately and wait for the final outcome of the division¡¯s

sale

C. Cancel the project immediately as there is no need for integration with the

corporation¡¯s systems

D. Continue with the project until the division¡¯s sale is finalized

69. ¹«Ë¾µÄÒ»¸ö×Ó¹«Ë¾³Ð½ÓÁËÒ»¸öΪÆÚÒ»ÄêµÄ¼¯³ÉÏîÄ¿¡£ÔÚµÚ¶þ¸öÔµף¬ÏîĿ״̬±¨¸æÏÔʾ

ÏîÄ¿°´¼Æ»®½øÕ¹¡£¹«Ë¾°ì¹«ÊÒÐû²¼¸Ã×Ó¹«Ë¾½«ÔÚÈý¸öÔÂÄÚ³öÊÛ¡£ ÏîÄ¿¾­Àí½ÓÏÂÀ´Ó¦¸ÃÔõô×ö£¿

A. ÓëÏîÄ¿·¢ÆðÈ˺͹ؼü¸ÉϵÈ˹µÍ¨£¬ºËʵÏîÄ¿ÊÇ·ñÈÔÈ»ÓÐ¹Ø B. Á¢¼´ÖÕÖ¹ÏîÄ¿£¬µÈ´ý×Ó¹«Ë¾³öÊÛ

C. Á¢¼´È¡Ïû¸ÃÏîÄ¿£¬ÒòΪ²»ÔÚÐèÒª¸Ã¼¯³ÉÏîÄ¿ D. ¼ÌÐø½øÐиÃÏîÄ¿£¬ÖªµÀ¸Ã²¿ÃÅ×îºó±»ÊÕ¹º

70.Before developing a project charter, the project manager works with a consultant and subject matter experts to determine any constraints. Which of the following techniques did the project manager use? A. Lessons learned

B. Historical information C. Strategic plan D. Expert judgment

70. ÖÆ¶¨ÏîĿճÌ֮ǰ£¬ÏîÄ¿¾­ÀíÓëÒ»Ãû¹ËÎʺÍÖ÷Ìâר¼ÒÒ»ÆðºÏ×÷È·¶¨ÈκÎÖÆÔ¼ÒòËØ¡£ÏîÄ¿

¾­ÀíʹÓÃÁËÏÂÁÐÄÄÒ»Ïî¼¼Êõ£¿ A. ¾­Ñé½Ìѵ B. ÀúÊ·ÐÅÏ¢ C. Õ½ÂԼƻ® D. ר¼ÒÅжÏ

71.To report the quality test results on the deliverables, what should the project manager take to the stakeholders meeting? A. Work performance reports

B. Updated quality management plan C. Process improvement plan D. Quality control measurements

71. ΪÁ˱¨¸æ¿É½»¸¶³É¹ûÉϵÄÖÊÁ¿²âÁ¿½á¹û£¬ÏîÄ¿¾­ÀíÓ¦¸ÃЯ´øÊ²Ã´²ÄÁϲμӸÉϵÈË»áÒ飿

A. ¹¤×÷¼¨Ð§±¨¸æ

B. ¸üеÄÖÊÁ¿¹ÜÀí¼Æ»® C. ¹ý³Ì¸Ä½ø¼Æ»® D. ÖÊÁ¿¿ØÖƺâÁ¿

72.A project manager assigns an activity to a team member. The team member performs the activity as the understood. However, the results do not meet the project manager¡¯s expectations

To avoid this situation, what tool should have been used? A. Interactive communication B. Active listening C. Encode and decode D. Push communication

72. ÏîÄ¿¾­Àí½«Ò»Ïî»î¶¯·ÖÅ䏸ÍŶӳÉÔ±¡£ÍŶӳÉÔ±°´ÆäÀí½âÖ´Ðл¡£µ«ÊÇ£¬Ö´Ðнá¹ûδ

ÄÜÂú×ãÏîÄ¿¾­ÀíµÄÆÚÍû¡£

Ϊ±ÜÃâÕâÖÖÇé¿ö£¬ÏîÄ¿¾­ÀíÓ¦¸ÃÊÂÏÈʹÓÃʲô¹¤¾ß£¿ A£® ½»»¥Ê½¹µÍ¨ B£® »ý¼«ÇãÌý C£® ±àÂëºÍ½âÂë D£® ÍÆÊ½¹µÍ¨

73.Due to unavoidable circumstances, a project is terminated before it is completed. What should the project manager do to close the project?

A. Prepare the change management documentation

B. Prepare formal documentation indicating why the project terminated C. Update the benefits realization documentation D. Reassign the team members

73. ÓÉÓÚ²»¿É±ÜÃâµÄÇé¿ö£¬ÏîÄ¿ÔÚÍ깤ǰÖÕÖ¹¡£ÊÕβÏîĿʱ£¬ÏîÄ¿¾­ÀíÓ¦¸Ã×öʲô£¿

A. ×¼±¸±ä¸ü¹ÜÀíÎĵµ

B. ×¼±¸ÕýʽÎĵµËµÃ÷ÏîĿΪºÎÖÕÖ¹ C. ¸üÐÂÐ§ÒæÊµÏÖÎĵµ

D. ΪÍŶӳÉÔ±ÖØÐ·ÖÅäÈÎÎñ

74.A US$150,000 project requires the completion of the following tasks: Task 1 starts today and has an estimated duration of 2days

Task 2 cannot start until task 1 is finished and has an estimated duration of 8 days Task 3 cannot start until task 1 is finished, must be completed before task 4 starts, and has a duration of 4 days

Task 4 cannot start until task 2 is finished and has an estimated duration of 8 days Task 5 cannot start until task 4 is finished and has an estimated duration of 1 days What is the duration of the critical path? A. 15 days B. 17 days C. 19 days D. 23 days

74. Ò»¸ö¼ÛÖµ150,000ÃÀÔªµÄÏîĿҪÇóÍê³ÉÒÔÏÂÈÎÎñ£º

ÈÎÎñ1½ñÌ쿪ʼ£¬ÇÒ¹ÀËã³ÖÐøÊ±¼äΪ2Ìì¡£

ÈÎÎñ2ÒªÔÚÈÎÎñ1½áÊøÖ®ºó²ÅÄÜ¿ªÊ¼£¬ÇÒ¹ÀËã³ÖÐøÊ±¼äΪ8Ìì¡£

ÈÎÎñ3ÒªÔÚÈÎÎñ1½áÊøÖ®ºó²ÅÄÜ¿ªÊ¼£¬±ØÐëÔÚÈÎÎñ4¿ªÊ¼Ö®Ç°Íê³É£¬ÇÒ¹ÀËã³ÖÐøÊ±¼äΪ4Ìì¡£

ÈÎÎñ4ÒªÔÚÈÎÎñ2½áÊøÖ®ºó²ÅÄÜ¿ªÊ¼£¬ÇÒ¹ÀËã³ÖÐøÊ±¼äΪ8Ìì¡£ ÈÎÎñ5ÒªÔÚÈÎÎñ4½áÊøÖ®ºó²ÅÄÜ¿ªÊ¼£¬ÇÒ¹ÀËã³ÖÐøÊ±¼äΪ1Ìì¡£ ¹Ø¼ü·¾¶µÄ³ÖÐøÊ±¼äÊǶàÉÙ A. 15Ìì B. 17Ìì C. 19Ìì D. 23Ìì

75.Due to scope creep, project team members must work long hours which results in low morale. After a team member resigns, other team members must postpone vacations to maintain the project schedule

At the next projectreview board meeting, the project manager should do which of the following

A. Use the human resource management plan to request additional resources

B. Use the project management information system to request an extension to the

project schedule

C. Propose a change in scope to reduce the team¡¯s workload

ÁªÏµ¿Í·þ£º779662525#qq.com(#Ìæ»»Îª@)