四川省巴中至南充(南部)高速公路
水泥稳定碎石底基层、基层
施工技术指南
四川巴南高速公路有限责任公司
二0一一年
目 录
总 则………………………………………………………………………………… ·························· 错误!未定义书签。
1 施工准备工作 ········································································· 错误!未定义书签。 2碎石加工要求 ·········································································· 错误!未定义书签。 3材料的采集、进场与管理 ······················································ 错误!未定义书签。 4混合料组成设计 ······································································ 错误!未定义书签。 5 生产试验段 ············································································· 错误!未定义书签。 6 施工 ························································································· 错误!未定义书签。 7 施工质量控制和检验 ····························································· 错误!未定义书签。 8 环境保护措施 ········································································· 错误!未定义书签。
总 则
1、为严格施工程序,规范施工行为,统一质量标准,提高施工水平,确保高速度、高质量的建好高速公路,特制定”水泥稳定碎石底基层、基层施工技术指南”,望遵照执行。
2、为确保巴南高速公路沥青路面工程质量达到总体目标要求,在施工过程中做到有章可循、有据可依、减少盲目性,消除质量隐患,减少工程损失,特制定本指南。
3、本指南以四川省巴中至南充(南部)高速公路项目路面工程设计文件为依据,结合四川省交通运输厅下发的相关文件以及标准、规范、规程而制定。
4、路面垫层、底基层和基层施工,一律要求采用集中厂拌、摊铺机摊铺。要求施工单位按照《招标文件》要求,配备足够的拌和、运输、摊铺、压实机械,确保基层和底基层的施工质量。
5、路面垫层、底基层施工,必须在经过验收合格的路床上进行,没有通过验收的路段,不允许进行路面底基层施工。
6、水泥稳定碎石底基层、基层施工技术,除应符合本指南外,还应符合国家现行有关规范、标准的规定。
1
1 技术准备工作
1.1 组织准备
1.1.1根据设计文件、合同任务及路基施工的实际条件编制周密的施工组织计划,包括制定施工方案、水泥稳定碎石底基层与基层施工的工艺流程、总体进度计划(含网络)、机械、劳力配置及材料供应计划等具体安排,建立质量保证体系和有关规章制度。
1.1.2水泥稳定碎石底基层与基层施工是多工种、机械化、工厂化野外群体作业,必须建立严密的施工管理体系和效率高、反应快的生产指挥系统,指挥系统内应设专职质量保证领导机构。
1.1.3根据施工需要,组建工地试验室,要有资质母体试验室授权,配备足够的试验、检测仪器和具有资质的试验人员,所有仪器设备要经有资质的计量部门标定认证,并通过质监部门验收认可。
1.1.4 上述准备事项必须书面报送业主和监理工程师审批。 1.2 技术准备
1.2.1施工技术管理人员应熟悉设计文件、招标文件、有关规范和标准,了解工程全貌、沿线自然条件,明确设计意图和要求,实地核实、审查图纸,掌握工程要点,提出需要设计单位作技术交底的问题;进一步明确、部署、安排施工初步方案,并搜集有关新技术、新工艺、新材料、新设备等资料。
1.2.2 必须开办短期培训班,举办技术讲座,对专业技术人员、技术工人和农民工进行培训,学习各自岗位对应的技术规范、质量管理、操作技能、操作规程、安全要领,提高质量意识、遵守职业道德,掌握“应知”“应会”。确保技术交底至每一位参建人员,特别是一线操作手。留下培训记录备查。
1.2.3组织人员调查沿线筑路材料、劳动力、能源、工程用水的分布、交通运输现状、居民点、厂矿企业、其他工程建设等情况。提供材料供应和储备、环保治安等初步实施方案,报监理工程师审批。
2