processes.
C. Negotiate a compromise with the seller.
D. Reject the change request and insist that the seller perform to the contract she signed. 90. ÄãÊÇһλ¸ºÔð´óÐÍÈí¼þÕûºÏÏîÄ¿µÄÏîÄ¿¾Àí£¬ÏîÄ¿Éæ¼°ºÜ¶àÂô·½¡£ÆäÖÐһλÖ÷ÒªÂô·½·ÇÕýʽµØÇëÇó±ä¸ü²É¹º¹¤×÷˵Ã÷Ê飬ÏëÔö¼ÓһЩ֮ǰºöÂÔµÄÐèÇó¡£ÄãÈ·¶¨ÕâÑù×ö»áÔö¼ÓÏîÄ¿µÄʱ¼äºÍ³É±¾¡£ÄãÓ¦¸ÃÈçºÎÓ¦¶ÔÂô·½ÇëÇó£¿
A£®ºÍ²É¹º°ì¹«ÊÒÒ»Æð£¬´ÓÆäËüÂô·½ÄÇÀïÖØÐ»ñµÃ¹ØÓڲɹº¹¤×÷˵Ã÷ÊéµÄ±êÊé¡£ B£®Ïêϸ·ÖÎöһϱä¸üÇëÇóµÄÄÚÈÝ£¬È»ºó½«ÕâЩÐÅÏ¢·´Ó³ÔÚÏîÄ¿¼Æ»®ºÍ²É¹º¹ý³ÌÀï¡£ C£®ºÍÂô·½ÐÉÌÒ»¸öÕÛÖԵĽâ¾ö·½°¸¡£
D£®¾Ü¾ø±ä¸üÇëÇ󣬼á³ÖÈÃÂô·½°´ÕÕºÏͬʵʩÏîÄ¿¡£
91. You are a project manager in a large organization that uses a matrix structure for projects. You have been asked to investigate what organizational structure your competitors use and how this affects their ability to manage projects successfully. How would you describe the MAIN difference between a matrix organization and a functional organization?
A£® In a functional organization, project managers have more authority than they do in a matrix organization.
B£® More people work full-time on projects in a functional organization than in a matrix organization.
C£® Project team members usually report to two bosses in a matrix organization;the functional manager and the project manager.
D£® Most companies have found that functional organization structures provide the most flexibility for managing projects.
91. ÄãÊÇÒ»¸ö´óÐÍ×éÖ¯µÄÏîÄ¿¾Àí£¬¸Ã×éÖ¯µÄÏîÄ¿²ÉÓþØÕó½á¹¹ÐÎʽ¡£¹ÜÀí²ãÒªÇóÄãµ÷²é¾ºÕù¶ÔÊÖʹÓõÄ×éÖ¯ÀàÐÍÒÔ¼°¶ÔÏîÄ¿¹ÜÀíµÄÓ°Ïì¡£ÄãÈçºÎÃèÊö¾ØÕó×éÖ¯ºÍÖ°ÄÜ×éÖ¯µÄÖ÷񻂿±ð£¿
A£®ÔÚÖ°ÄÜ×éÖ¯ÖУ¬ÏîÄ¿¾ÀíÓµÓнϴóµÄȨÁ¦¡£ B£®Ö°ÄÜ×éÖ¯µÄ³ÉÔ±¶¼ÊÇȫְ×öÏîÄ¿¡£
C£®¾ØÕó×éÖ¯ÖУ¬ÍŶӳÉԱͨ³£ÏòÖ°ÄܾÀíºÍÏîÄ¿¾Àíͬʱ»ã±¨¹¤×÷¡£ D£®´ó¶àÊý¹«Ë¾ÈÏΪְÄÜ×éÖ¯½á¹¹¸ü¾ßÁé»îÐÔ¡£
92. If a project manager is concerned with gathering, integrating, and disseminating the outputs of all project management processes, she should concentrate on creating a better: A. WBS.
B. Communications management plan.
C. Project management information system. D. Project scope management plan.
92. Èç¹ûÏîÄ¿¾ÀíÕýÔÚ¹Ø×¢ÊÕ¼¯¡¢ÕûºÏÒÔ¼°·¢²¼ËùÓÐÏîÄ¿¹ÜÀí¹ý³ÌµÄÊä³ö£¬Ëý×îºÃÓ¦¸ÃÖÆ¶¨ÒÔÏÂÄÄÏîÄÚÈÝ£¿ A£®¹¤×÷·Ö½â½á¹¹¡£ B£®¹µÍ¨¹ÜÀí¼Æ»®¡£ C£®ÏîÄ¿¹ÜÀíÐÅϢϵͳ¡£ D£®ÏîÄ¿·¶Î§¹ÜÀí¼Æ»®¡£
PMP¿¼ÊÔ£¬²»½ö½öÊÇÄõ½Ö¤Ê飬¸üÊÇÏîÄ¿¹ÜÀíÀíÄîµÄÌáÉýÓë½ø½×£¡
33
93. You are the project manager on a project that has a total project float of negative 20. What should you do FIRST?
A. Use less experienced team members.
B. Request an extension of the project due date. C. Acquire more resources for critical path activities.
D. Fast track the project if overall project risk is already too high. 93. Ä㸺ÔðµÄÏîÄ¿µÄ×ܸ¡¶¯Ê±¼äÊÇ-20£¬ÄãÊ×ÏÈÓ¦¸Ã×öʲô£¿ A£®Ê¹ÓÃûÓй¤×÷¾ÑéµÄÍŶӳÉÔ±¡£ B£®ÒªÇó¸øÏîÄ¿ÑÓÆÚ¡£
C£®¸ø¹Ø¼ü·¾¶»î¶¯»ñµÃ¸ü¶à×ÊÔ´¡£
D£®Èç¹ûÏîÄ¿·çÏÕÒѾºÜ¸ßµÄÇé¿öÏÂÐèÒª¿ìËÙ¸ú½øÏîÄ¿¡£
94. You are given a new project to manage and a brief project scope statement. The project sponsor tells you that there is no required completion date for the project. The BEST thing to do is to:
A. Ask for better definition of the project scope before accepting the project. B. Accomplish the project as time allows.
C. Plan the project as you would a normal project, but build in schedule flexibility. D. Make a list of activities that need to be done.
94.·ÖÅ䏸ÄãÁËÒ»¸öÐÂÏîÄ¿£¬²¢ÇÒÖÆ¶¨Á˼òµ¥µÄÏîÄ¿·¶Î§ËµÃ÷Êé¡£·¢ÆðÈ˸æËßÄ㣬ûÓиøÏîÄ¿¹æ¶¨¾ßÌåµÄÍ깤ÈÕÆÚ¡£´Ëʱ£¬Äã×îÓ¦¸Ã×öµÄÊÂÇéÊÇʲô£¿ A£®ÔÚ½ÓÊÜÏîĿ֮ǰҪÇóÒ»·Ý¶¨Òå¸üÏêϸµÄ·¶Î§ËµÃ÷Êé¡£ B£®Ë³Æä×ÔÈ»µØÊµÊ©ÏîÄ¿¡£
C£®ÏñÆäËüÆÕͨÏîĿһÑù¸øÏîÄ¿½øÐй滮£¬µ«½ø¶ÈµÄÖÆ¶¨¿ÉÒÔÁé»îЩ¡£ D£®ÂÞÁÐÒ»¸öÐèÒªÍê³É¹¤×÷µÄÇåµ¥¡£
95. Warranty and inventory costs are going up, causing the project manager to worry about the costs of nonconformance. What is the BEST advice you can give the project manager? A. Increases scrap. B. Increase rework..
C. Perform a quality audit. D. Look for benchmarks.
95. µ£±£¼°¿â´æ³É±¾²»¶ÏÉÏÉý£¬Ê¹µÃÏîÄ¿¾Àí·Ç³£µ£ÐÄ·ÇÒ»Ö³ɱ¾¡£Äã¸øÏîÄ¿¾ÀíµÄ×î¼Ñ½¨ÒéÊÇ£º
A£®Ôö¼Ó·ÑÁÏ¡£ B£®Ôö¼Ó·µ¹¤¡£ C£®ÊµÊ©ÖÊÁ¿É󼯡£ D£®Ñ°ÕÒ»ù×¼¡£
96. A project manager is quantifying risks for her project. Several of her experts are off-site, but wish to be included in the risk assessment portion of the project. How can this be done? A£® Use Monte Carlo simulation through Internet as a tool.
PMP¿¼ÊÔ£¬²»½ö½öÊÇÄõ½Ö¤Ê飬¸üÊÇÏîÄ¿¹ÜÀíÀíÄîµÄÌáÉýÓë½ø½×£¡
34
B£® Apply the critical path method. C£® Do a brainstorming.
D£® Apply the Delphi technique.
96. Ò»ÃûÏîÄ¿¾ÀíÕýÔÚΪ×Ô¼ºµÄÏîÄ¿½øÐÐÁ¿»¯¡£¼¸Î»²ÎÓëÏîÄ¿µÄר¼Ò¶¼²»ÔÚÏÖ³¡£¬µ«ÊÇÏ£Íû²ÎÓëÏîÄ¿·çÏÕÆÀ¹À¹¤×÷¡£ÈçºÎʵÏÖÕâÒ»µã£¿ A. ÒÀÍÐÒòÌØÍø£¬Ê¹Óà Monte CarloÄ£Äâ·½·¨¡£ B. ʹÓùؼü·¾¶·¨¡£ C. ½øÐÐÍ·ÄԷ籩¡£ D. ʹÓà Delphi¼¼Êõ¡£
97. Project manager issue reports on the amount of testing done throughout the life of the project. However, Testing is only a minor aspect of the quality control plan. It would be BEST for the project manager to:
A. Issue the report, as this is a major stakeholder, her needs would have been included in the staffing management plan.
B. Not issue the report, project resources should be expended on communicating information that contributes to success.
C. Request details of the information the stakeholder needs in the report. Provide that information to those handling the quality control function on the project.
D. Have the stakeholder meet with the project sponsor to get the sponsor¡¯s agreement that project funds should be expended on this effort.
97. ÏîÄ¿µÄ¹µÍ¨¹ÜÀí¼Æ»®ÒѾÍê³É£¬²¢µÃµ½Á˿ͻ§µÄÅú×¼¡£´Ëʱ£¬Ò»Î»Ö÷Òª¸ÉϵÈËÒªÇóÏîÄ¿¾Àí±¨¸æÕû¸öÏîÄ¿ÉúÃüÖÜÆÚÖеIJâÊÔÊýÁ¿¡£È»¶ø£¬²âÊÔÖ»ÊÇÖÊÁ¿¿ØÖƼƻ®Öв»Ì«ÖØÒªµÄÄÚÈÝ¡£ÏîÄ¿¾ÀíµÄ×î¼Ñ×ö·¨ÊÇʲô:
A. ·¢²¼±¨¸æ£¬ÒòΪËýÊÇһλÖ÷ÒªµÄ¸ÉϵÈË£¬ÈËÔ±Å䱸¹ÜÀí¼Æ»®ÖÐÒª°üÀ¨ËýµÄÐèÇó¡£ B. ¾Ü¾ø·¢²¼±¨¸æ£¬ÏîÄ¿×ÊÔ´Ó¦¸ÃʹÓÃÔÚÓÐÖúÓÚÏîÄ¿³É¹¦µÄ¹µÍ¨ÐÅÏ¢ÉÏ¡£
C. ÊÕ¼¯Õâλ¸ÉϵÈËËùÐèµÄÐÅϢϸ½Ú£¬È»ºó½«ÕâЩÐÅÏ¢Ìṩ¸øÏîÄ¿ÉϸºÔðÖÊÁ¿¿ØÖƵÄÈËÔ±¡£ D. ÈøÉϵÈ˺ͷ¢ÆðÈ˼ûÃæ£¬ÒÔÕ÷µÃ·¢ÆðÈËͬÒ⽫ÏîÄ¿·ÑÓÃʹÓÃÔÚÕâÏîÄÚÈÝÉÏ¡£
98. Senior management asks the project manager how the project would be affected if two resources were removed from the project. To calculate a response, the project manager should complete:
A. Resource leveling.
B. What-if scenario analysis. C. Schedule compression. D. Fast tracking.
98. ¸ß¼¶¹ÜÀí²ãѯÎÊÏîÄ¿¾Àí£¬Èç¹û´ÓÏîÄ¿Öгéµ÷Á½Ïî×ÊÔ´ÊÇ·ñ»á¶ÔÏîÄ¿Ôì³ÉÓ°Ïì¡£ÏîÄ¿¾ÀíÓ¦¸ÃÍê³ÉÒÔÏÂÄÄÏîÀ´»Ø´ð¹ÜÀí²ãµÄÎÊÌâ: A£®×ÊԴƽºâ¡£ B£®¼ÙÉèÇé¾°·ÖÎö¡£ C£®½ø¶ÈѹËõ¡£ D£®¿ìËÙ¸ú½ø¡£
PMP¿¼ÊÔ£¬²»½ö½öÊÇÄõ½Ö¤Ê飬¸üÊÇÏîÄ¿¹ÜÀíÀíÄîµÄÌáÉýÓë½ø½×£¡
35
99. You have just completed the design phase for a client¡¯s project and are about to enter the implementation phase. All of the following need to be done EXCEPT: A. Lessons learned. B. Updating records. C. Formal acceptance.
D. Completion of the product of the project.
99. ÄãµÄÏîÄ¿¸Õ¸ÕÍê³ÉÁËÉè¼Æ½×¶Î½øÈ뵽ʵʩ½×¶Î¡£´Ëʱ£¬ÒÔϾùÊÇÐèÒªÍê³ÉµÄÄÚÈÝ£¬³ýÁË£º A. ×ܽá¾Ñé¡£ B. ¸üмǼ¡£ C. ÕýʽÑéÊÕ¡£ D. Íê³ÉÏîÄ¿²úÆ·¡£
100. If a project manager focuses on ensuring that the project satisfies the needs for which it was undertaken, the project manager is involved in: A. Cost management. B. Time management. C. Quality management. D. Scope management.
100. Èç¹ûÏîÄ¿¾ÀíÒ»Ö±¹Ø×¢È·±£ÏîÄ¿Âú×ãÐèÇó£¬ÏîÄ¿¾ÀíÕý´¦ÓÚ£º A£®³É±¾¹ÜÀí¡£ B£®Ê±¼ä¹ÜÀí¡£ C£®ÖÊÁ¿¹ÜÀí¡£ D£®·¶Î§¹ÜÀí¡£
101. A new project manager asks you what the 50/50 rule is used for. You would reply: A. Crashing. B. Quality.
C. Performance reporting. D. Cost estimating.
101. һλÐÂÏîÄ¿¾ÀíÎÊÄãÈçºÎʹÓÃ50/50¹æÔò£¬ÄãµÄ»Ø´ðÊÇ£º A. ¸Ï¹¤¡£ B. ÖÊÁ¿¡£ C. ¼¨Ð§±¨¸æ¡£ D. ³É±¾¹ÀËã¡£
102. While evaluating the bar chart, the project manager determines that the project is behind schedule. What should she do?
A. Obtain approval from the customer to slip the project. B. Report finding to management.
C. Evaluate the alternatives with the team. D. Evaluate the alternatives with the customer.
102. ÔÚÆÀ¹À¸ÊÌØÍ¼Ê±ÏîÄ¿¾Àí·¢ÏÖÏîÄ¿½ø¶ÈÂäºó£¬ËýÓ¦¸ÃÔõô×ö£º A£®¾ÍÏîÄ¿ÑÓÆÚ»ñµÃ¿Í»§µÄͬÒâ¡£
PMP¿¼ÊÔ£¬²»½ö½öÊÇÄõ½Ö¤Ê飬¸üÊÇÏîÄ¿¹ÜÀíÀíÄîµÄÌáÉýÓë½ø½×£¡
36