2012.11.06 SD-DOP-DPP-ST-50 生活楼5、6层吊装方案 5 rev.0 - 图文 下载本文

COOEC 海油工程

SD-DOP-DPP-ST-

Figure 4.3c The EL.(+)45 250 to EL.(+)47 750 of LQ turn over 90olocation of crane

图4.3c 生活楼5,6层翻转90o吊车站位

LF 7-2 DPP MODULE SHOP DESIGN LIFTTING

PLAN FOR EL.(+)45 250 TO EL.(+)47 750 OF LQ

Page 21 of 45

COOEC 海油工程

SD-DOP-DPP-ST-

Figure 4.3d The EL.(+)45 250 to EL.(+)47 750 of LQ turn over 180olocation of crane

图4.3d 生活楼5,6层翻转180o吊车站位 After the panel has been lifted to a suitable height as requirement, cranes move toward the center of 4# skid way. After the cranes move to the assembly location, put the panel onto the temporary supports slowly. The assembly location of cranes is shown in figure 4.3f-4.3g. Ensure the panel is stable and remove the hook.

吊机向滑道中心方向行走,对正总组位置后缓慢下降,吊车总组站位如图4.3e-4.3g所示。确认生活楼5,6层完全受力稳定后进行吊车摘钩,吊车退出吊装场地。

LF 7-2 DPP MODULE SHOP DESIGN LIFTTING

PLAN FOR EL.(+)45 250 TO EL.(+)47 750 OF LQ

Page 22 of 45

COOEC 海油工程

SD-DOP-DPP-ST- Figure 4.3e The original assembly location of cranes for EL.(+)45 250 to EL.(+)47 750 of LQ

图4.3e 生活楼5,6层总组吊车初始站位

Figure 4.3f The final assembly location of cranes for EL.(+)45 250 to EL.(+)47 750 of LQ

图4.3f 生活楼5,6层总组吊车就位站位 LF 7-2 DPP MODULE SHOP DESIGN LIFTTING

PLAN FOR EL.(+)45 250 TO EL.(+)47 750 OF LQ

Page 23 of 45

COOEC 海油工程

SD-DOP-DPP-ST-

Figure 4.3g Side elevation of 600T crane

图4.3g 600T吊机站位侧视图

LF 7-2 DPP MODULE SHOP DESIGN LIFTTING

PLAN FOR EL.(+)45 250 TO EL.(+)47 750 OF LQ

Page 24 of 45